What Members Should Know
The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.
State jurisdictional interconnection requests are categorized into three separate processes in the regulations.
Review Chapter 314Interconnection Levels
The appropriate process depends on the size and qualification of the small generating facility.
Up to 500 kW
A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.
Up to 2 MW
A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.
Other SGFs
A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.
Small Generator Interconnection Resources
Use the resources below to review the interconnection queue, find answers to common questions, contact REC or access the application materials.
Virginia Interconnection Regulations
Review the complete Regulations Governing Interconnection of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.