Solar generation facility
Solar Solutions

Small Generator
Interconnection

Learn about the process for connecting a small generating facility to REC's electric system.

Getting Started

What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional interconnection requests are categorized into three separate processes in the regulations.

Review Chapter 314

Interconnection Levels

The appropriate process depends on the size and qualification of the small generating facility.

1
Level 1

Up to 500 kW

Certified SGF

A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

2
Level 2

Up to 2 MW

Certified SGF

A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

3
Level 3

Other SGFs

Additional Review

A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

Virginia Interconnection Regulations

Review the complete Regulations Governing Interconnection of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

REC STORIES

REC Wraps Up the 2023 Farmer's Market Season

Monday | September 18, 2023
The season of Farmers Markets wrapped up, keeping employees busy with connecting with members.

Putting the WoW Factor in Career Expo

Sunday | September 17, 2023
Apprentice Linemen Kevin Ryan and Hunter Jost met with students at the Worlds of Work (WoW) career expo to share about their job and responsibilities ...

2023 Louisa Biz Expo

Saturday | September 16, 2023
Hosted by the Louisa Chamber of Commerce, the Louisa Biz Expo provides businesses the opportunity to connect with others and the community.