What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

To view the Rappahannock Interconnection Queue and Frequently Asked Questions, please visit the Virgina Small Generation Interconnection Portal here

For all other questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC Hosted Telephone Town Hall

Thursday | August 23, 2018
On Thursday, August 23 REC hosted the 2018 Telephone Town Hall event. REC invited a random sample of over 40,000 members to participate in the call. N...

REC Warns of Phone Scam

Tuesday | August 21, 2018
REC have received phone calls from scammers claiming to be from REC stating the members’ accounts are overdue. The scam calls have been received by me...

REC Members Elect Peers to Lead Co-op

Thursday | August 16, 2018
REC members selected three of their peers to serve on REC’s Board of Directors. More than 6,400 members participated in the election by returning thei...