What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

To view the Rappahannock Interconnection Queue and Frequently Asked Questions, please visit the Virgina Small Generation Interconnection Portal here

For all other questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC's Board of Directors fully respects our members and the democratic process of governing their Cooperative.

REC Warns of Potential Scammers

Wednesday | June 6, 2018
REC urges members to beware of anyone calling to demand immediate payment for services from the co-op. Callers may claim the electric service will be ...

REC Restoration Efforts Near Completion

Wednesday | May 16, 2018
REC and mutual aid crews worked through the night to restore service to members who lost power during what the National Weather Service described as a...